Audit P0 Release Scope And Roadmap

Goal

Reconcile the P0 product, architecture, delivery task list, and Kanban plan into a clear release-scope closure plan.

Sources

Context

Most P0 implementation tasks are now in Done, while the remaining active and backlog tasks include several P1/P2 product extensions. Continuing directly into the current Ready implementation task would improve resource health diagnostics, but it may not be the highest-leverage path for closing the P0 release.

This task is a planning and scope-convergence pass. It should identify what is already good enough for P0, what must still be fixed before release, and which tasks should be moved or rewritten as P1/P2 follow-up work.

In Scope

  • Review P0 product, architecture, operation, check/index, schema, starter, and view-query documents for current P0/P1 boundaries.
  • Review the current Forma task board view and task metadata against the P0 boundary.
  • Produce a P0 release bar with must-have, should-have, and deferred items.
  • Identify any missing P0 closure tasks with observable acceptance criteria.
  • Recommend task board changes as a dry-run table, including tasks to keep Ready, move to Backlog, split, cancel, or defer to P1/P2.
  • Call out source-stability and release-readiness risks such as unpushed local commits or missing validation evidence.

Out Of Scope

  • Product code changes.
  • Implementing health, graph, search, metadata edit, or proposal workflows.
  • Changing P0 architecture decisions without a separate approved capture.
  • Moving Kanban cards without maintainer approval.
  • Release publishing or GitHub Actions release execution.

Acceptance Criteria

  • The report lists completed P0 capabilities and the remaining P0 closure gaps.
  • The report separates P0 release blockers from P1/P2 follow-ups.
  • Each recommended new or changed task has a target Kanban column and rationale.
  • The report identifies at least one next executable task or states that P0 is ready for release validation.
  • The report cites the project knowledge and task board sources used.
  • No repository code or task implementation is changed.

Relationship Notes

This task should run before continuing into P1/P2 implementation work. Its output may update roadmap, tasks, and Kanban after maintainer approval.

Delivery Notes

Open Questions